Skip to main content
Madison, WI Header
File #: 88860    Version: 1 Name: Accepting bituminous surface pavement constructed by Private Contract in Southern Addition to Birchwood Point Phase 5 - Surface Paving, Private Contract No. 9091
Type: Resolution Status: Items Referred
File created: 6/24/2025 In control: BOARD OF PUBLIC WORKS
On agenda: 7/15/2025 Final action:
Enactment date: Enactment #:
Title: Accepting bituminous surface pavement constructed by Private Contract in Southern Addition to Birchwood Point Phase 5 - Surface Paving, Private Contract No. 9091 (District 9)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 9091 Streets Schedule A bituminous.pdf

Fiscal Note

No City Funds required. Private contract.

Title

Accepting bituminous surface pavement constructed by Private Contract in Southern Addition to Birchwood Point Phase 5 - Surface Paving, Private Contract No. 9091 (District 9)

Body

WHEREAS, VH Birchwood Point, LLC has satisfactorily completed the installation bituminous surface pavement by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, for:  Southern Addition to Birchwood Point Phase 5 - Surface Paving.

NOW, THEREFORE, BE IT RESOLVED

 

That the bituminous surface street improvements on the following streets be and are hereby accepted:

 

                     Hazy Sky Parkway from 132 FT W of Barn Swallow Circle to Barn Swallow Circle

                     Hazy Sky Parkway from Barn Swallow Circle to Birch Blossom Road

                     Hazy Sky Parkway from Birch Blossom Road to E Lot Line of Lot 379

                     Twin Treasure Drive from 272 FT W of Birch Blossom Road to Birch Blossom Road

                     Barn Swallow Circle from Hazy Sky Parkway to 30 FT S of North Lot Line of Lot 440

                     Birch Blossom Road from Hazy Sky Parkway from Twin Treasure Drive

                     Birch Blossom Road from Twin Treasure Drive to North Lot Line of Lot 386

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 13852 by $38,583.61 for a useful life of 40 years.