Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810041-00-53B0953 $177,271.71
Acc't. No. CW53-58270-810079-00-53B0953 $71,845.50
Acc't. No. ES01-58275-810054-00-53B0953 $194,493.00
Acc't. No. EW01-58273-810455-00-53B0953 (#W-6730) $575.00
Title
Improvements accepted for Jefferson Street Reconstruction Assessment District - 2003, Contract No. 5449. (13th AD)
Body
BE IT RESOLVED, that the street, water main, and storm and sanitary sewer improvements on Jefferson Street Reconstruction Assessment District - 2003 have been completed on 12/06/03 be and are hereby accepted.
Original Contract Sum $ 445,724.85
(Based on Actual Units) $ 447,110.21
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 2,925.00
Final Contract Amount $ 444,185.21