Legislation Details

File #: 93458    Version: 1 Name: Approving Plans, Specifications, And Schedule Of Assessments For Sugar Maple Lane Reconstruction Assessment District - 2025.
Type: Resolution Status: Items Referred
File created: 6/3/2026 In control: BOARD OF PUBLIC WORKS
On agenda: 6/23/2026 Final action:
Enactment date: Enactment #:
Title: Approving Plans, Specifications, And Schedule Of Assessments For Sugar Maple Lane Reconstruction Assessment District - 2025. (District 1)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 15417_FactSheet.pdf, 2. 15417_PrelimAssessments.pdf, 3. 15417_BPWMailAffidavit Sugar Maple.pdf, 4. 15417_Sugar Maple Lane_Preliminary Assessments - BPW Update.pdf, 5. 15417_Sugar Maple Lane_Preliminary Assessments - BPW Update.pdf
Fiscal Note
Funding is available in the 2026 Adopted Engineering-Major Streets Capital Budget in the Reconstruction Streets program. No additional appropriation is required.

Funds are available in Acct. No.
ACCOUNT # ACCOUNT NAME COST
15417-402-170 STREET $ 195,500.00
15417-402-174 STREET STORM $ 52,900.00
15417-84-174 STORMWATER NETWORK $ 706,100.00
15417-83-173 SANITARY SEWER $ 133,400.00
15417-86-179 WATER NETWORK $ 123,280.00
15417-402-177 STREET LIGHTING $ 9,500.00

TOTAL COST $ 1,220,680.00
ASSESSMENTS $ 963,172.06
CITY COST $ 257,507.94

Title
Approving Plans, Specifications, And Schedule Of Assessments For Sugar Maple Lane Reconstruction Assessment District - 2025. (District 1)
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of Sugar Maple Lane Reconstruction Assessment District - 2025 pursuant to a resolution of the Common Council, RES-25-00196, ID No. 87426, adopted 3/25/25, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.

BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $160,497.94 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines s...