Title
Improvements accepted for Sidewalk & Curb & Gutter, Citywide Installation & Repair, Contract No. 5997. (Various ADs)
Body
BE IT RESOLVED, that the improvements on Sidewalk & Curb & Gutter, Citywide Installation & Repair have been completed on 11/15/07 be and are hereby accepted.
Original Contract Sum $ 279,850.00
(Based on Actual Units) $ 233,342.17
Net Change by Change Orders $ 39,732.23 or 14.19%
Liquidated Damages $ 0.00
Final Contract Amount $ 273,074.40
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58280-810376-00-53W0417 $270,043.90
Acc't. No. CS53-58260-810358-00-53W0417 $3,030.50