Fiscal Note
The proposed resolution amends the adopted 2018 capital budget for the
Fire Department and Engineering-Facilities Management to reassign $820,6
14 of GO Borrowing to the
Fire Station #
14 project.
The current authorized budget for this project is 6,750,000 (MUNIS project 17451-30-
140)
to fund the following:
BID for Construction (Miron Construction Company): $6,390,783
4% Construction Contingency: $255,631
Professional Fees: $519,200
Site Development Costs: $35,000
Furnishing, Fixtures and Equipment $370,000
TOTAL $7,570,6
14Estimated total project cost is $7,570,6
14, or a difference of $820,6
14.
The proposed project funding is:
Current MFD Capital Budget: $6,750,000
2018 Engineering Sustainability Improvements Program (Rooftop Solar): $150,000
2018
Fire Department Facility Improvement Program: $200,000
2018
Fire Department Equipment Program: $320,6
14 2018
Fire Communications Equipment Program: $150,000
TOTAL $7,570,6
14The proposed resolution authorizes the award of Public Works Contract No.8027, Madison
Fire Station 14 with a reduced contingency of 4%, and amends the 2018 Adopted Capital Budgets of the
Fire Department and Engineering-Facilities Management to transfer general obligation borrowing from several projects into the
Fire Station 14 project. The transfers are as follows: $150,000 from Sustainability Improvements (Engineering-Facilities Management); $150,000 from
Fire Communications Equipment (
Fire Department); $200,000 from
Fire Building Improvements (Engineering-Facilities Management), and $320,6
14 from
Fire Equipment (
Fire Department).
11804-401-
140 ($150,000)
11804-401-801 ($150,000)
11800-401-
140 ($200,000)
11800-401-801 ($200,000)
17452-30-150 ($150,000)
17452-30-801 ($150,000)
10373-30-150 ($320,6
14)
13737-30-801 ($320,6
14)
17451-30-
140 $820,6
1417451-30-801 $820,6
14Title
SUBSTITUTE Awarding Public Works Contract No. 8027, Madison
Fire Station 14 and Amending the 2018 Adopted Capital Budgets of the
Fire Department a...
Click here for full text