File #: 46650    Version: 1 Name: Change Order No. 10 to Contract No. 7529, Reconstruction of the Madison Water Utility Operations Center, 110 S. Paterson Street, to Joe Daniels Construction Co., Inc., in the amount of $129,413.75, with a time extension of 40-days.
Type: Miscellaneous Status: Approved
File created: 3/28/2017 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 4/5/2017
Enactment date: Enactment #:
Title: Change Order No. 10 to Contract No. 7529, Reconstruction of the Madison Water Utility Operations Center, 110 S. Paterson Street, to Joe Daniels Construction Co., Inc., in the amount of $129,413.75, with a time extension of 40-days.
Attachments: 1. leg 46650 - co 10-7529.pdf

Title

Change Order No. 10 to Contract No. 7529, Reconstruction of the Madison Water Utility Operations Center, 110 S. Paterson Street, to Joe Daniels Construction Co., Inc., in the amount of $129,413.75, with a time extension of 40-days.